Project Information

Client:
Landsec
Main Contractor:
Sir Robert McAlpine
Sector:
Commercial
Duration:
11 Months
Services:
Installation of base build security systems

Scope of Works

Our scope of works for this project consisted of the installation of both internal and external CCTV, a full access control system and an intercom system, all based over the client’s IP network.

Also included was the security room furniture was also included in our scope of works along with a dedicated lift access control integration system to the scenic lifts, which was a major component of the project.

Challenges Overcome

One of the main challenges surpassed by our team was the booking and planning of deliveries, due to the location of the building, which is next to the Barbican and directly above Moorgate Station, as well as a lack of a store loading area.

Another challenge overcome seamlessly was cabling the access control and lift integration works through the scenic lift shafts.

Back to Projects
back