Project Information

Client:
Knights Garden Centre
Main Contractor:
Gratte Brothers Catering Equipment Limited
Sector:
Leisure
Duration:
2 Weeks
Services:
Foodservice Solutions

Project Details

Working with Knight’s selected builder, Gratte Brothers installed a freezer, walk-in cold rooms, an all-in-one cook suite, dish-washing and drying areas, a combi oven, front of house display and all bar bottle cold storage. The running of external duct-work was sensitively installed to fit the garden environment.

The project was disrupted by major roadworks leading to the site, causing a 6-month delay to the necessary utility upgrades. Making the best of the situation, Gratte Brothers demobilised and rearranged the commissioning and training programme to be available as soon as the council would allow works to begin.

The Victorian walled garden was listed as a Finalist in Horticulture Week’s Catering Excellence Awards 2017.

Back to Projects
back
to top